Roles
-PO/Architect = Hillary
-Developers
= Frank
= Dan B.
= Jeff
-Testers
= Dan S.
= Darren
-Publications
= Collin
-Quality Assurance
= Darren
Developers and Testers
Get Github. It is going to be our version control system.
Milestones
-End of week 1
------------------
Solid specification
Solid UML
Git hub configured and ready to use
Collin able to start writing out customers/employees/dvds in text format
-End of week 2
------------------
Class structure completed
GUI basics complete and GUI functionality should be started
-End of week 3
------------------
Program complete
-PO/Architect = Hillary
-Developers
= Frank
= Dan B.
= Jeff
-Testers
= Dan S.
= Darren
-Publications
= Collin
-Quality Assurance
= Darren
Developers and Testers
Get Github. It is going to be our version control system.
Milestones
-End of week 1
------------------
Solid specification
Solid UML
Git hub configured and ready to use
Collin able to start writing out customers/employees/dvds in text format
-End of week 2
------------------
Class structure completed
GUI basics complete and GUI functionality should be started
-End of week 3
------------------
Program complete